Time & material tag · customer copyOct 26, 2026
Northside Electric
Extra work order
No.1002
- Project
- Harborview Medical Office, Level 2 TI
- General contractor
- Coastline Builders
- Location
- Level 2 nurse station
- Work asked for by
- Mike Alvarez, Coastline Builders
Description of extra work
Add dedicated circuit for nurse station printer
Installed one dedicated 20A circuit from panel LP-2 to the nurse station for an owner-furnished printer added after rough-in. Outside original scope.
| Class | Crew | Hrs | Rate | Amount |
|---|---|---|---|---|
| Journeyman | 1 | 3.5 | $85.00 | $297.50 |
| Item | Qty | Each | Amount |
|---|---|---|---|
| 12/2 MC cable | 75 ft | $1.25 | $93.75 |
| 20A single-pole breaker | 1 ea | $18.00 | $18.00 |
- Labor
- $297.50
- Markup on labor 15%
- $44.63
- Material
- $111.75
- Markup on material 15%
- $16.76
- Total
- $470.64
Photos
Accepted by general contractor

Mike Alvarez · Oct 28, 2026, 8:20 AM PDT · signed by private link