Time & material tag · customer copyOct 8, 2026
Northside Electric
Extra work order
No.1001
- Project
- Lincoln Elementary Modernization
- General contractor
- Summit General
- Location
- Classroom wing B
- Work asked for by
- Dana Whitfield, Summit General
Description of extra work
After-hours fire alarm device relocation
Relocated four fire alarm notification devices in Classroom Wing B after hours to suit revised ceiling heights, as directed by Dana Whitfield of Summit General. Outside original scope.
| Class | Crew | Hrs | Rate | Amount |
|---|---|---|---|---|
| Foreman | 1 | 6 | $95.00 | $570.00 |
| Journeyman | 1 | 6 | $85.00 | $510.00 |
| Item | Qty | Each | Amount |
|---|---|---|---|
| Fire alarm cable | 150 ft | $0.85 | $127.50 |
- Labor
- $1,080.00
- Markup on labor 15%
- $162.00
- Material
- $127.50
- Markup on material 15%
- $19.13
- Total
- $1,388.63
Accepted by general contractor

Dana Whitfield · Oct 8, 2026, 8:20 AM PDT · signed in person