Time & material tag · customer copyNov 14, 2026
Northside Electric
Extra work order
No.1002
- Project
- Lincoln Elementary Modernization
- General contractor
- Summit General
- Location
- Admin office 104
- Work asked for by
- Dana Whitfield, Summit General
Description of extra work
Add data drops in admin office
Installed six additional data drops in Admin Office 104 at the owner's request, relayed by Dana Whitfield of Summit General. Outside original scope.
| Class | Crew | Hrs | Rate | Amount |
|---|---|---|---|---|
| Journeyman | 2 | 3.5 | $85.00 | $595.00 |
| Item | Qty | Each | Amount |
|---|---|---|---|
| Cat6 plenum cable | 300 ft | $0.42 | $126.00 |
| Cat6 jack and faceplate | 6 ea | $9.50 | $57.00 |
- Labor
- $595.00
- Markup on labor 15%
- $89.25
- Material
- $183.00
- Markup on material 15%
- $27.45
- Total
- $894.70
Accepted by general contractor
Not signed yet