Time & material tag · customer copyNov 6, 2026
Northside Electric
Extra work order
No.1001
- Project
- Pier 9 Warehouse Retrofit
- General contractor
- Bayline Construction
- Location
- Bay 4
- Work asked for by
- Priya Shah, Bayline Construction
Description of extra work
Reroute feeder around new mezzanine steel
Rerouted the 200A feeder in Bay 4 around mezzanine steel added after conduit was installed, as directed by Priya Shah of Bayline Construction. Outside original scope.
| Class | Crew | Hrs | Rate | Amount |
|---|---|---|---|---|
| Foreman | 1 | 4 | $95.00 | $380.00 |
| Journeyman | 2 | 6 | $85.00 | $1,020.00 |
| Item | Qty | Each | Amount |
|---|---|---|---|
| 2in EMT conduit | 60 ft | $4.10 | $246.00 |
| 2in EMT coupling | 8 ea | $6.25 | $50.00 |
- Labor
- $1,400.00
- Markup on labor 15%
- $210.00
- Material
- $296.00
- Markup on material 15%
- $44.40
- Total
- $1,950.40
Photos
Accepted by general contractor

Priya Shah · Nov 6, 2026, 7:20 AM PST · signed in person