Pier 9 Warehouse Retrofit

General contractor: Bayline Construction

Contract rules

9 confirmed
Written notice of a change or claim
7 days Section 8.4, page 3
Who can authorize changes
Contractor's Project Manager, Contractor's Project Executive Section 8.2, page 3
Written authorization before starting
Yes, required Section 8.3, page 3
Markup cap on labor
15% Section 8.6, page 3
Markup cap on materials
15% Section 8.6, page 3
Markup cap on equipment
15% Section 8.6, page 3
Required T&M labor rates
Not in contract
T&M tickets submitted or signed within
1 day Section 8.7, page 3
Priced change order request due within
14 days Section 8.5, page 3

A reading aid, not legal advice.

Valdek read these from the subcontract for this job, and the owner confirmed each one. In your own account you upload the contract as a PDF or as photos of the pages.