Pier 9 Warehouse Retrofit

One note, every document

Pier 9 Warehouse Retrofit · Nov 21, 2026

What the foreman said

“Me, Luis and Danny on Pier 9 today, 8 hours each. Pulled the feeders to panel LP-2 and set the high bay lights in bays 4 and 5. Tom had us move the exit sign at the north door of bay 6 for the new egress path, that took Luis 2 hours. Lost about 3 hours this morning, the racking crew had bays 1 and 2 blocked off. Need to know where panel LP-3 goes now that the mezzanine stair moved, E3.1 still shows it on the old wall. Fixtures came at 7. Did a toolbox talk on the lifts.”

Valdek splits it into the drafts below. In your own account the foreman checks and approves each one. Nothing is saved or sent before that.

The daily report, with crew hours

Northside Electric

Daily report

Nov 21, 2026

Project
Pier 9 Warehouse Retrofit
General contractor
Bayline Construction
Weather
-

Work performed

Pulled feeders to panel LP-2. Set high bay lights in bays 4 and 5. Relocated the exit sign at the north door of bay 6 (extra work, Tag #1003).

Crew and hours

NameTypeReg.OT
Sam OrtizForeman8-
Luis VegaJourneyman8-
Danny ChoApprentice8-

3 people, 24 hours (2 on extra work, 22 on contract work)

Extra work today (T&M tags)

  • Tag #1003: Relocate exit sign for revised egress path

Deliveries

Light fixtures, 7:00 am

Delays

Bays 1 and 2 blocked off by the racking crew (9 hours lost)

Safety

Toolbox talk on lift use

Prepared by Sam Ortiz.

The hours on the extra-work tag come out of the day's hours, so the two always agree. If a tag ever claims more hours than the crew worked, Valdek flags it. The same hours fill the weekly timesheet for payroll.

The extra work, as a tag

The delay, for the delay log

Could not work in bays 1 and 2

Why
Waiting on another trade
Who caused it
Racking installer
Crew hours lost
9

The racking crew had bays 1 and 2 blocked off until about 10 am.

One tap drafts a written notice of delay from this entry and the job's contract rules. The letter is a template to have an attorney review.

The open question, as an RFI

Northside Electric

Request for information

RFI 1

Draft

Project
Pier 9 Warehouse Retrofit
Reference
E3.1
Answer needed by
Nov 24, 2026

Panel LP-3 location

Drawing E3.1 shows panel LP-3 on the wall where the mezzanine stair now lands. Where does the panel go?

Asked by Sam Ortiz.

The foreman sends it to the GC as a private link. The GC answers on that page with no account. If the answer creates extra work, a tag is started that points back to the RFI.