Contract check

Written notice due Nov 28, 2026

7 days after the work, per your contract rules (Section 8.4)

Counted in calendar days. The contract does not say which kind of day, so the earlier date is used.

6 days left

In your own account, one tap here drafts the notice letter on your letterhead, citing the section.

Tom Reyes can't authorize changes on this job.

The contract rules name: Priya Shah, Contractor's Project Manager, Contractor's Project Executive (Section 8.2, page 3). It also wants extra work authorized in writing before it starts.

One tap asks for it in writing
Priya Shah, Per our conversation with Tom Reyes on site on Nov 21, 2026, we were directed to relocate exit sign for revised egress path at North exit, Bay 6 on Pier 9 Warehouse Retrofit. This work is outside our original scope and we are tracking it as time and material. Please reply to confirm in writing that this work is authorized. Our subcontract (Section 8.3, page 3) calls for this in writing. Sam Ortiz Northside Electric

This tag is priced over what the contract allows.

  • Markup on labor is 20%. The contract allows 15% (Section 8.6, page 3).

The GC can reject the difference. Edit the tag to bring it in line, or keep it if you have a reason.

From the contract rules you confirmed for this job. A reading aid, not legal advice.

Time & material tag · customer copyNov 21, 2026

Northside Electric

Extra work order

No.1003

Project
Pier 9 Warehouse Retrofit
General contractor
Bayline Construction
Location
North exit, Bay 6
Work asked for by
Tom Reyes, Bayline Construction

Description of extra work

Relocate exit sign for revised egress path

Relocated one exit sign at the north exit of Bay 6 to match the revised egress path. Outside original scope.

Labor
ClassCrewHrsRateAmount
Journeyman12$85.00$170.00
Material
ItemQtyEachAmount
LED exit sign1 ea$64.00est$64.00
12/2 MC cable30 ft$1.25$37.50
Labor
$170.00
Markup on labor 20%
$34.00
Material
$101.50
Markup on material 15%
$15.23
Total
$320.73

Accepted by general contractor

Not signed yet