Sample data. Northside Electric and everything in it is made up. Nothing here can be changed.
This tag is waiting on the GC. In your own account you would hand them your phone, or text them a private link to sign.

Contract check

Written notice due Nov 26, 2026

7 days after the work, per your contract rules (Section 8.4)

Counted in calendar days. The contract does not say which kind of day, so the earlier date is used.

4 days left

In your own account, one tap here drafts the notice letter on your letterhead, citing the section.

From the contract rules you confirmed for this job. A reading aid, not legal advice.

Time & material tag · customer copyNov 19, 2026

Northside Electric

Extra work order

No.1002

Project
Pier 9 Warehouse Retrofit
General contractor
Bayline Construction
Location
Bays 1 and 2
Work asked for by
Priya Shah, Bayline Construction

Description of extra work

Temporary power for racking installer

Provided and connected a temporary 100A panel in Bays 1 and 2 for the racking installer at the request of Priya Shah of Bayline Construction. Outside original scope.

Labor
ClassCrewHrsRateAmount
Journeyman14$85.00$340.00
Apprentice14$55.00$220.00
Material
ItemQtyEachAmount
Temporary panel and cords1 lot$180.00est$180.00
Labor
$560.00
Markup on labor 15%
$84.00
Material
$180.00
Markup on material 15%
$27.00
Total
$851.00

Accepted by general contractor

Not signed yet